15 hours ago · This was because one of the main contractors for the DTL2, Alpine Bau (which was building King Albert Park, Sixth Avenue and Tan Kah Kee), went bankrupt in mid-2013. On 28 June 2015, Transport Minister Lui Tuck Yew announced that the delay was "completely resolved" by the authorities and Stage 2's opening date was brought forward to 27 December 2015.